1. If the project does not intend to claim costs for the extra 3 months beyond the end of the project implementation:
The LP will have to submit the following documents within 2 months after the end of the project implementation:
- the last regular progress report (original paper signed version + electronic version)
- the Closure Report (electronic version only)
- the CD-ROM
- the supporting documents indicated in the administrative closure checklist (electronic version)
2. If the project intends to claim costs for the extra 3 months beyond the end of the project implementation:
The LP will have to submit the following documents within 2 months after the end of the project implementation:
- the last regular progress report (original paper signed version + electronic version)
- the Closure Report (electronic version only)
- the CD-ROM
Once these documents have been delivered to the JTS, the LP will then ask the JTS for the additional financial report template.
For further details